Education Building Assessment and Repair


Education Building Assessment and Repair

Education Building Assessment and Repair

Want to learn more about this project?

Let's Talk

About this project

Lerch Bates designed repairs for a building that was experiencing water intrusion issues around the perimeter of the 7th floor and at the expansion joint on the east side of the building. Lerch Bates was retained to complete a condition assessment to identify the cause and origin and determine appropriate next steps.

Following this investigation, Lerch Bates provided designer of record services including schematic design narrative, design development submittals, and construction documents. Lerch Bates continued to assist the team throughout the bidding and construction administration phase services. These services included:

  • Conducting the pre-bid meeting
  • Review of bid packages
  • Attending contractor pre-construction meetings
  • Attending pre-installation meetings
  • Participating in weekly coordination meetings
  • Providing weekly site observations with reports
  • Conducting final punch list review and verification

 

Repair + ModerniseEnclosures & StructuresHigher Education